Annual Street Resurfacing Project 2020 - Upcoming Road Closures

Work on the following streets will be completed this week 11/9/2020 - 11/13/2020:

Street Dates Work Type Closure or Traffic Control
Capitol Ave from Runnymede to Cul-de-Sac 11/11-11/12 Slurry Seal Closure
Scofield from Woodland to Cooley 11/9 Slurry Seal Closure
Newbridge from Bay to Saratoga 11/10 Slurry Seal Closure
Holland St from E Bayshore to Menalto 11/9 Overlay Closure
Bradley Way from Bay Road to Holland 11/9 Overlay Closure
Menalto Ave from E Bayshore to Bay 11/9 Overlay Closure
W Bayshore from 1833 W Bayshore to Woodland 11/10 Overlay Two-Way Lane TCP
Pulgas Ave from Gaillardia to E Bayshore 11/9-11/12 Grind, Overlay Two-Way Lane TCP
Runnymede St from University to 433 ft east of Cooley 11/9 & 11/11 Grind on 11/9, Overlay on 11/11 Closure
O'Connor St from Clarke to Pulgas 11/9 Slurry Seal Closure

 

The road closures will be in effect between the hours of 8:00am and 5:00pm on the days specified above.

During these times the roads will be closed to through traffic and access to residents will be closed until the materials have dried.  Residents are asked to notify City Staff for issues that arise due to these closures.

We will try to minimize your inconvenience. NO PARKING signs will be posted in the affected areas to inform you of the work and their dates.

For comments or questions regarding the construction of this project, please contact Bryan Mendes with Teichert at (925) 460-7399 or Adrian Biggs with The City of East Palo Alto at (650) 338-8404.