Work on the following streets will be completed this week 11/9/2020 - 11/13/2020:
Street | Dates | Work Type | Closure or Traffic Control |
---|---|---|---|
Capitol Ave from Runnymede to Cul-de-Sac | 11/11-11/12 | Slurry Seal | Closure |
Scofield from Woodland to Cooley | 11/9 | Slurry Seal | Closure |
Newbridge from Bay to Saratoga | 11/10 | Slurry Seal | Closure |
Holland St from E Bayshore to Menalto | 11/9 | Overlay | Closure |
Bradley Way from Bay Road to Holland | 11/9 | Overlay | Closure |
Menalto Ave from E Bayshore to Bay | 11/9 | Overlay | Closure |
W Bayshore from 1833 W Bayshore to Woodland | 11/10 | Overlay | Two-Way Lane TCP |
Pulgas Ave from Gaillardia to E Bayshore | 11/9-11/12 | Grind, Overlay | Two-Way Lane TCP |
Runnymede St from University to 433 ft east of Cooley | 11/9 & 11/11 | Grind on 11/9, Overlay on 11/11 | Closure |
O'Connor St from Clarke to Pulgas | 11/9 | Slurry Seal | Closure |
The road closures will be in effect between the hours of 8:00am and 5:00pm on the days specified above.
During these times the roads will be closed to through traffic and access to residents will be closed until the materials have dried. Residents are asked to notify City Staff for issues that arise due to these closures.
We will try to minimize your inconvenience. NO PARKING signs will be posted in the affected areas to inform you of the work and their dates.
For comments or questions regarding the construction of this project, please contact Bryan Mendes with Teichert at (925) 460-7399 or Adrian Biggs with The City of East Palo Alto at (650) 338-8404.